ID | Task Name | Duration | Start | Finish | Remarks |
1. | Orientation Week | 5 days | 6th July 1998 (Mon) | 10th July 1998 (Fri) | - |
2. | Visual Basic Foundation | 14 days | 13th July 1998 (Mon) | 30th July 1998 (Thu) | Excluding Saturdays and Sundays. |
3. | Evaluation of Four VB Internet Libraries, plus two more. | 7 days | 27th July 1998 (Mon) | 4th August 1998 (Tue) | Excluding Saturdays and Sundays. |
4. | Project: Web URLs Validator (WebVat) | 52 days | 5th August 1998 (Wed) | 9th August 1998 (Fri) | Excluding Saturdays, Sundays and Public Holiday (10th August 98) |
5. | Issues surrounding the Building of Project ABBA | 40 days | 17th August 1998 (Mon) | 9th October 1998 (Fri) | Excluding Saturdays and Sundays. |
6. | Web Documentation | 70 days | 13th July 1998 (Mon) | 16th October 1998 (Fri) | Excluding Saturdays and Sundays. |
7. | Updating Robocup Bibliographies | 20 days | 17th August 1998 (Mon) | 9th October 1998 (Fri) | Excluding Saturdays and Sundays. This is done on alternate weeks. |
8. | Gathering Robocup Teams '98 - Paris | 40 days | 24th August 1998 (Mon) | 16th October 1998 (Fri) | Excluding Saturdays and Sundays. |
9. | Project Documentation | 40 days | 7th September 1998 (Mon) | 16th October 1998 (Fri) | - |
Created on 25th August 1998. Last revised 16th October 1998.
Creator : Daniel
Chua